As part of the County’s current resurfacing project, the section of Amwell Road (CR 514) from Route 206 to Beekman Lane will be milled and repaved. In conjunction with this milling and paving, a Road ...
The Engineering Department has an update on the 2025 Road Paving Program. So far, Falcon Road, Kilmer Drive, Matthew Road, Daniel Drive, Walnut Grove Road, and Township Line Road have been completed.
The 2025 Road Paving Program has been finalized. The following roads are scheduled to be repaved this year: Beverely Drive, Kilmer Drive, Fern Way, and Gail Court; Briar Way; Scott Drive; Barbara Driv...
Phase I of the Capital Road Paving will be completed by September 27, 2024. Fairfield Lane, Harford Place, Hunt Club Road, Stonewain Street and Valinor Road is fully repaved.
1. Pour concrete footings for bridge across from Lake Drive, (which will be the new Valley Road intersection). The steel plates you see sticking up is a coffer dam which keeps water away fr...
The Year of Roads Continues! Mayor Robert Britting, Jr. continues his transparency campaign and informs residence of the progress on Route 206, Falcon Road, and other Hillsborough Road projects.
The New Jersey Department of Transportation has released the following statement in response to the question of the identity of the equipment and workers currently on the job site of the Route 206 Co...